Project schedule network diagrams
“Project Schedule Network Diagrams” is an output for the process “Sequence Activities”.
A project schedule network diagram is a graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities. Figure 6-11 illustrates a project schedule network diagram. A project schedule network diagram is produced manually or by using project management software. It can include full project details, or have one or more summary activities. A summary narrative can accompany the diagram and describe the basic approach used to sequence the activities. Any unusual activity sequences within the network should be fully described within the narrative.
A B C D E Begin H F G End I J K L FF FS + 15 SS + 10 SS Figure 6-11. Project Schedule Network Diagram
“Project Schedule Network Diagrams” is an input for the process “Develop Schedule”.
The project schedule network diagrams contain the logical relationships of predecessors and successors that will be used to calculate the schedule.
This definition was found in the PMBOK V5