Project calendars

Project calendars

Below are the description of all the uses of the working document “Project calendars”:

“Project Calendars” is an output for the process “Develop Schedule”.
A project calendar identifies working days and shifts that are available for scheduled activities. It distinguishes time periods in days or parts of days that are available to complete scheduled activities from time periods that are not available. A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the project schedule. The project calendars may be updated.

“Project Calendars” is an input for the process “Control Schedule”.
A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the schedule forecasts.

This definition was found in the PMBOK V5

Go back to the Glossary or to the Mapping